Frontier Communications is scheduled to commence fiber installation in the Heritage Colony subdivision (see attached). The MUD district has been contacted and they will provide utility map locations for water and sanitary sewer as well as being available to make repairs if needed. Location marking services and door hanger distribution will commence next week with actual directional drilling anticipated to start 08/31/2022.
Contact information:
- Contractor:
- Future Infrastructure LLC
Steve Wagner: 972-322-2313
- Future Infrastructure LLC
- Onsite Contact:
- Future Infrastructure LLC
Osmar Bernal: 281-387-2609
- Future Infrastructure LLC
- Municipal District Services:
- First Colony MUD #9
281-290-6500
- First Colony MUD #9